CUC CurrentCUC is on target to complete the restoration of all re-connectable customers islandwide within the 90-day period projected after Hurricane Ivan. There are approximately 1,700 customers still awaiting restoration and CUC expects to complete these reconnections by 1 December. The majority reside along the northern end of West Bay Road where reconnection began on Wednesday (24 Nov) and will be completed early next week. With the rebuilding of lines nearly complete, CUC service crews will remain in the districts to continue reconnecting customers who become approved. These customers are asked to contact the utility’s office at 949-4300 to schedule reconnection. For those who have completed repairs to their dwelling and need to schedule re-inspection, they are asked to contact the Planning Department at 916-5873. The CUC crews will be concentrating on restoring streetlights around the island and has set mid-December as target completion date. A continued rebuilding of the infrastructure will also continue with work to enhance reliability of service, repairs to the submarine cable at Rum Point, and repairs to the North Sound Road plant.
| ||||||||||||||||||||||||||||||||||||||||||||